Construction again disrupts Canada Line service for five weeks

By Richmond Sentinel

Published 10:41 PST, Mon January 16, 2023

Service on the Canada Line between Bridgeport and Richmond–Brighouse stations will be temporarily impacted from today through Feb. 17. 

Service will end at 9:30 p.m. on weekdays, about four hours early, allowing construction crews to continue work on the new Capstan station. Regular service will resume on Feb. 18.

These temporary impacts will mainly affect customers travelling to and from Bridgeport, Aberdeen, Lansdowne, and Richmond–Brighouse stations. Extra bus service will be available between Bridgeport and Richmond–Brighouse stations, with buses stopping at each impacted station and running about every 10 minutes.

The temporary service changes are necessary to ensure the safety of workers and the public, as crews will be using a large crane to begin installing escalators and station roofs. The crane cannot be used safely above the track while trains are in operation.

Capstan station remains on track to open later this year.